+86-372-2266616

info@batchingplantsupplier.com

HZS50 Concrete Batching Plant Installed in Mexico

This concrete plant was installed in Mexico City in September 2025, under a steel roof on the customer’s own yard.

Project Overview

The HZS50 concrete plant stands on a level pad inside a steel shed. The roof keeps the rain off the belts, the scales and the operator, which matters in a city with a long rainy season. Everything arrived as one shipment: the batching machine, the mixer tower, the silos, the screw conveyors and the control cabinet. The photos on this page were taken while the steel was going up and the last connections were being made, so the guards and covers are not all in place yet. The site sits in the hills around Mexico City, and the shed was finished before the plant arrived. That order is the right one for a stationary concrete batching plant: pads first, steel second, cables last.

Customer Background

The customer makes concrete in Mexico City. Plenty of work, but not much space: a big concrete plant asks for a big piece of land, a deep foundation and weeks of steel work, and a yard inside the city cannot give any of that. HZS50 concrete batching plant was the answer to that. 50 m³/h is enough for a local supplier or a precast yard, and the whole line fits under a roof. The customer also wanted the concrete plant covered. In the rainy season an open plant stops for water on the belt and mud around the pads; under a shed the crew keeps working.

Customer Requirements

  1. Fit the yard. The HZS50 concrete batching plant had to stand inside the existing steel shed and still leave a lane for the wheel loader.
    2. 50 m³/h, not more. The customer didn’t want to pay for capacity the local demand wouldn’t use, and the mixer truck fleet had to match the plant.
    3. One mixer that keeps up. A full 1 m³ batch every minute, one after the other, with no waiting at the tower.
    4. Correct cement weight. Cement is the expensive part of the mix, so the cement scale had to hold ±1%.
    5. Easy truck movement. 3800 mm of clearance under the discharge hopper, so a standard mixer truck can drive in, load, and leave.
    6. Simple control. One cabinet with a screen and a pendant remote, so one man can run the plant and still walk around it.
    7. Guidance during erection. Erection and commissioning support plus operator training, so the HZS50 concrete batching plant starts clean.

AGICO Customized Solution

  1. A bolted stationary frame — The tower ships as modules and is bolted on site, not welded. A small crane can lift the parts inside a shed, and the frame can be taken down and moved later if the yard changes.
  2. JS1000 twin-shaft mixer — Two shafts turn against each other, so the batch moves in two directions at once and is mixed in 45 to 60 seconds. The tray is reinforced and lined with wear plates.
  3. PLD1600 aggregate batcher — The bins sit above load cells, and each aggregate is weighed before it leaves the machine. The batcher is sized to feed a 1 m³ batch without a second pass.
  4. Cement on its own scale — Cement comes out of the silo through a screw conveyor and is weighed to ±1% before it drops into the hopper. Fly ash and additive are weighed on their own scales.
  5. 3800 mm under the hopper — The discharge door is pneumatic and opens fully, so a standard truck loads without reversing twice. The height matches common mixer trucks on the road.
  6. Cabinet plus pendant — The automatic control system stores the recipes and records each batch. The pendant remote lets the operator jog the plant during cleaning or a check.
  7. Dust kept inside — Inlets are sealed and the mixer hopper has covers. If the yard is tight, a dust collector on the silo keeps the air around the plant clean.
  8. Foundation plan first — The layout and the foundation drawing go out with the order, so the shed and the pads can be finished before the steel arrives. That is what happened on this site.

Installation Process

Work starts at the foundation. The four legs of the mixer tower are set on anchor bolts and braced, then the platform and the mixer are lifted on top. The batching machine and the silos sit on their own pads, and the screw conveyors are lined up between the silo outlet and the cement weighing hopper. When the steel is square, the air lines, the water line and the cables are pulled and the plant is run empty before the first batch.

In the photos the frames are already up. The crew is working from scaffolding, and the control cabinet is standing beside the tower with its pendant remote on a cable, so the operator can walk around the machine during the test run. What is left at this stage is the small work: guards, covers and paint touch-up.

AGICO HZS50 Concrete Batching Plant Mexico City Plant Site View
AGICO HZS50 Concrete Batching Plant Mexico City Mixer Tower

Project Results

Customer Feedback

“The plant fits in the space we had, and the loader can still move around it. AGICO sent the foundation plan before the steel arrived, so the shed was ready when the trucks came. The first batches were on weight, and the drivers had no trouble under the hopper.”

— Customer, Mexico City, Mexico

Need Similar Concrete Batching Plant for Your Project?

Tell AGICO your required capacity, project location, and budget. We will provide a free customized batching plant solution within 24 hours.

AGICO
GET IN TOUCH

We are committed to keeping your inbox free from spam. We will only send you relevant and important information.