HZS50 Concrete Batching Plant Installed in Russia
Project Overview
- Plant Model: HZS50, stationary
- Capacity: 50 m³/h, 60 s cycle
- Mixer Type: JS1000A twin-shaft, 4.2 m hydraulic discharge
- Application: Russia construction onsite
- Delivery Time: 20–25 days
- Installation Time: 14–21 days on site
Customer Background
Customer Requirements
- Beat the season. The HZS50 concrete plant had to be erected and tested inside the working window, not after it.
- Ship the silo in sections. A welded shell is a heavy, awkward load; the customer wanted panels that travel on a standard truck.
- Feed from bags. Cement comes in bulk bags on this site, so the intake had to sit at ground level, and the conveyor had to lift at a steep angle.
- Empty cleanly in frost. No pockets in the cone, no cement left in the conveyor tube after the shift.
- Hold the cement weight. Cement is the expensive part; the scale had to stay within ±1%.
- One operator. A centralized panel with automatic, semi-automatic, and manual modes, so one man can run a batch and still walk the plant.
- Support after the sale. Erection guidance, operator training, and spare parts, because the site is a long way from the factory.
AGICO Customized Solution
- HZS50 line, matched to the job — 50 m³/h with a 60-second cycle, JS1000A mixer and PLD1600 batcher. The output fits a local supplier or a project site without the concrete of a bigger plant sitting in the drum.
- Bolted silo, 60 t + 100 t — Detachable panels, bolted on site. The silo carries a dust collector, a level monitor and a pressure relief valve, and the ladder and top railing are part of the package.
- LSY219 screw conveyor — The tube lifts cement at the angle the layout allows, and the intake hopper sits at ground level, which is what a bag-fed site needs. ø219 mm and ø273 mm sizes are both available.
- PLD1600 aggregate batcher — Two to four bins, a 1.6 m³ weighing hopper and pneumatic doors on each compartment. The scale works to ±2%, and the buffer keeps the reading steady while the belt or hopper is moving.
- JS1000A twin-shaft mixer — Two shafts turn against each other and finish a batch in 60 seconds. The blades and arms are wear-resistant, and the mixer takes aggregate up to 80/60 mm.
- Centralized control — Automatic, semi-automatic and manual modes on one panel. Recipes are stored, batches are recorded, and the manual mode is there for cleaning and for the first test run.
- Dust collection on the powder side — A dust collector on the silo top and secondary collection at the transfer points. On a site ringed by trees, that is also what keeps the neighbours quiet.
- Pads, layout and levelling — The pad positions and the steel layout are fixed before the frame arrives, so the crane has one lift per section. Because the frame is bolted, it can be re-levelled later if the ground moves with the frost.
Installation Process
The order of work on site is simple. The pads go down first. The four legs of the silo frame are set on the anchor bolts and braced. The silo shell follows, panel by panel, bolted from the ladder. Then the cone, the discharge valve, and the top railing. The screw conveyor is lined up between the silo outlet and the mixer, and the second one is set on its ground stand with the intake hopper at the bottom.
The long conveyor is the part that needs care. It runs at a steep angle, so the intake has to sit low enough to be fed from the ground and the head has to meet the silo inlet without a kink. In the video, the crew is kneeling at the intake, checking the connection before the first load.
The weather sets the pace. Spring on this site means mud, and the photos were taken between rains. Gravel was spread over the yard so the crane and the trucks could work, and the pads were kept above the water line.


Project Results
- Daily Output: 50 m³/h on paper, and 60 seconds per batch in practice. A short Russian season still gets a full year of work out of the plant.
- Labor Cost: One operator at the panel and one man on the bag hopper. The plant does not need a fitter standing next to it.
- Mixing Efficiency: The twin-shaft mixer works the whole batch at once and finishes in 60 seconds, so the truck does not sit under the hopper.
- Product Quality: Cement and fly ash are weighed to ±1%, aggregate to ±2%, each on its own scale. The mix holds its recipe from the first batch of the morning to the last one.
- ROI Period: The equipment is in the $35,000–$60,000 band. On a steady commercial workload at 50 m³/h, the plant is normally paid back within 12 to 24 months; send us your concrete price and daily volume and our engineers will run your own figure.
Customer Feedback
“The season here is short, so we could not wait. The silo came in panels, and the crane had it up in two days. The conveyor takes cement straight from the bags we get, and in the cold the cone empties without us going up there with a hammer.”
— Customer, Russia